UPGRADING OF GUA MUSANG CARRIAGEWAY

INFRASTRUCTURE WORKS

The works at Segment 5 and Section 3F involved the construction of eco-bridges to keep wildlife in the vicinity safe from traffic during animal crossings.
Minimum forest clearing activities were undertaken in both areas to lessen the impact on the natural habitat and food resources of wildlife.

Location : Gua Musang, Pahang :
1.   JKR Road Route 8 from Kg. Relong to Kg.Sg yu (Segment 5);
2.   JKR Road Routes 8 and 9 from Kg.Sg yu to Kg.Kubang Rusa (Section 3F)
Client/Owner : Public works Department Malaysia (Jabatan kerja Raya Malaysia or JKR)
Project duration : 54 months (2008 - 2013) for Segment 5
36 months (2010 - 2013) for Section 3F
Iconic Awarded Design : Package 3 (Section 3F1)
1)First Runner Up
Innovative Project Management 2014 by the Ministry of Works Malaysia
2)Winner
MINO Best Project Award 2017 (Category 1 - High Volume Road)